Task Scheduling Critical Path Method (CPM) Duration Analysis

Candidate Latency (1M Rows)
0.86 ms
(1.3x slower than golden)
Golden Latency (1M Rows)
0.68 ms
DuckDB in-memory engine
Underlying Data Volume
5 rows
220 B across 1 table
Evaluated Model
gemini-3.8-flash-low
Gen Latency: 8.6s
✔ Correctness Verified on 1M+ Records
Candidate SQL output matches ground truth golden query across all multiset rows and numeric tolerances (tol=1e-3). Zero data skew or anti-patterns detected on full dataset scale.

1. Analytical Significance & What It Means

Scenario & Frontier Trap
Business Scenario & Problem

Project managers identify the 'Critical Path'—the longest sequence of dependent tasks that dictates the minimum project completion time.

⚡ The Frontier Trap (Why LLMs Fail)

Adding task durations without considering parallel execution branches yields an unrealistically inflated project timeline.

Prompt / User Request Given to Model
Project managers identify the 'Critical Path'—the longest sequence of dependent tasks that dictates the minimum project completion time.

Execute the required analytical SQL calculation in DuckDB.
Expected output columns: task_code, critical_path_duration, path_str.
Results should be ordered as specified.

2. Underlying Tables, Row Counts & Data Volume

1 Tables (5 rows • 220 B)

Production-scale fixtures loaded into the isolated DuckDB sandbox with at least 1,000,000 records per table:

📊 project_tasks 5 rows 220 B Data Volume
task_code (VARCHAR) prerequisite_code (VARCHAR) duration_days (INTEGER)
Data Preview (showing sample rows from 5 total rows):
# task_code prerequisite_code duration_days
1 START NULL 0
2 DESIGN START 10
3 BUILD_FRONTEND DESIGN 15
4 BUILD_BACKEND DESIGN 25
5 DEPLOY BUILD_BACKEND 5

3. Graphical Query Execution Plan & Cost Bottlenecks

Physical Operator Tree (DuckDB 2.0 Profiler)

Visual flowchart of the physical execution pipeline. Operators with high relative costs (≥ 20% of query runtime or heavy latency) are visually highlighted:

Pipeline Latency Distribution (Total Plan Time: 0.86 ms) Nodes consuming ≥ 20% of query runtime are highlighted with glowing borders
✂️ TOP_N 7.0%
Latency: 0.06 ms
Rows In/Out: 1
Data Vol: 4,132 B
🔄 RECURSIVE_CTE 🔥 67.0% Cost
Latency: 0.58 ms
Rows In/Out: 5
Data Vol: 180 B
⚠️ Heavy Execution Bottleneck (67.0% of query runtime)
📐 PROJECTION 0.1%
Latency: 0.00 ms
Rows In/Out: 1
Data Vol: 36 B
📁 Projections: ['task_code', 'cumu...
🔍 TABLE_SCAN 3.4%
Latency: 0.03 ms
Rows In/Out: 1
Data Vol: 20 B
📁 memory.main.project_tasks
📐 PROJECTION 3.0%
Latency: 0.03 ms
Rows In/Out: 4
Data Vol: 0.02 MB
📁 Projections: ['task_code', '(cum...
⚡ HASH_JOIN 17.3%
Latency: 0.15 ms
Rows In/Out: 4
Data Vol: 0.01 MB
🔍 RECURSIVE_CTE_SCAN 0.6%
Latency: 0.01 ms
Rows In/Out: 5
Data Vol: 180 B
🔍 TABLE_SCAN 1.7%
Latency: 0.01 ms
Rows In/Out: 5
Data Vol: 436 B
📁 memory.main.project_tasks
Operator Cost % Latency Processed Rows Data Volume Details / Table Status
RECURSIVE_CTE 67.0% 0.58 ms 5 0.00 MB - 🔥 BOTTLENECK
HASH_JOIN 17.3% 0.15 ms 4 0.01 MB - Normal
TOP_N 7.0% 0.06 ms 1 0.00 MB - Normal
TABLE_SCAN 3.4% 0.03 ms 1 0.00 MB memory.main.project_tasks Normal
PROJECTION 3.0% 0.03 ms 4 0.02 MB Projections: ['task_code', '(cumulative_days + d Normal
TABLE_SCAN 1.7% 0.01 ms 5 0.00 MB memory.main.project_tasks Normal
RECURSIVE_CTE_SCAN 0.6% 0.01 ms 5 0.00 MB - Normal
PROJECTION 0.1% 0.00 ms 1 0.00 MB Projections: ['task_code', 'cumulative_days', 'p Normal

4. Queries Executed (Candidate vs Golden Ground Truth)

Beautified & Syntax Highlighted
Candidate SQL Executed by gemini-3.8-flash-low (Runtime on 1M Rows: 0.86 ms)
WITH RECURSIVE task_paths AS
  (SELECT task_code,
          duration_days AS cumulative_days,
          task_code AS path_str
   FROM project_tasks
   WHERE prerequisite_code IS NULL
   UNION ALL SELECT t.task_code,
                    p.cumulative_days + t.duration_days,
                    p.path_str || ' -> ' || t.task_code
   FROM task_paths p
   JOIN project_tasks t ON p.task_code = t.prerequisite_code)
SELECT task_code,
       cumulative_days AS critical_path_duration,
       path_str
FROM task_paths
ORDER BY cumulative_days DESC
LIMIT 1;
Golden Reference Ground Truth SQL (Runtime on 1M Rows: 0.68 ms)
-- Find the longest path (Critical Path) from START to DEPLOY
 WITH RECURSIVE task_paths AS
  (SELECT task_code,
          duration_days AS cumulative_days,
          task_code AS path_str
   FROM project_tasks
   WHERE prerequisite_code IS NULL
   UNION ALL SELECT t.task_code,
                    p.cumulative_days + t.duration_days,
                    p.path_str || ' -> ' || t.task_code
   FROM task_paths p
   JOIN project_tasks t ON p.task_code = t.prerequisite_code)
SELECT task_code,
       cumulative_days AS critical_path_duration,
       path_str
FROM task_paths
ORDER BY cumulative_days DESC
LIMIT 1;
DuckDB Fixture Setup DDL & Data Population
CREATE TABLE project_tasks (task_code VARCHAR, prerequisite_code VARCHAR, duration_days INT);


INSERT INTO project_tasks
VALUES ('START', NULL, 0),
       ('DESIGN', 'START', 10),
       ('BUILD_FRONTEND', 'DESIGN', 15),
       ('BUILD_BACKEND', 'DESIGN', 25),
       -- Longest branch
 ('DEPLOY', 'BUILD_BACKEND', 5);

5. Query Results & Expected Ground Truth

Tabular Comparison
Actual Candidate Output (1 rows × 3 cols)
# task_code critical_path_duration path_str
1 DEPLOY 40 START -> DESIGN -> BUILD_BACKEND -> DEPLOY
Expected Golden Output (1 rows × 3 cols)
# task_code critical_path_duration path_str
1 DEPLOY 40 START -> DESIGN -> BUILD_BACKEND -> DEPLOY